Rowwalker · by SunLean AI

AI that inspects piles and trackers.
Proof it was done right.

Rowwalker turns drone or phone photos of a solar site into a design-vs-actual report — tilt, rotation, height and XY for every pile — before the trackers go on.

30-minute call, a real site on screen
No hardware — phone or drone capture
Demo dataAs of Jul 23, 2026Piles installed 420 / 10,800 (3.9%)Inspected 204 (48.6%)Unresolved 3✕Critical open 0
B200%B190%B180%B170%B160%Collector substationB100%B110%B120%B130%B140%B150%B090%B080%B070%Wetland · no-buildB060%B050%Laydown yardB0158%B0220%B030%B040%BESS / O&M
N ↑
Not startedInstalled · uninspectedPassedOpen defectRework
200 m
Day 10
Historical record
Where we operate

20 GW of prospected inspection across three continents.

Where the crews are, the capture is: our SOP runs on any phone, and our drone partners fly where we do not have a team on the ground.

NORTH AMERICA
Pile and tracker verification. Drone partner network across the US.
EUROPE
Pile and tracker verification for tracker OEMs and EPCs.
ASIA
Utility-scale pile and tracker inspection.
Ask about your region
NORTH AMERICAACTIVEEUROPEACTIVEASIAACTIVE
What it finds

Walk one pile with Rowwalker.

Scroll. The photo is the evidence; the numbers are what the inspector would have had to measure by hand.

A single installed pile, head to grade, before the tracker goes on
PLUMBAXIS · 3.2°
DESIGN ELEVATIONACTUAL · −2.4 in
NO TORQUE STRIPE · 3 BOLTS
DEPTH 14 mm
B14-T44-P03
Tilt3.2° / ±1.0°✕FAIL
Rotation0.8° / ±4.0°●PASS
Height−2.4 in / ±1.0 in✕FAIL
Torque stripemissing · 3 bolts✕FAIL
Corrosionplate edge▲FLAG
Dent14 mm · torque tube▲FLAG
Embedment≥ 6.75 ft●PASS
Backfillcompacted●PASS
Pass20●PASS
Flag2▲FLAG
Fail2✕FAIL
Block B14 · 96 trackers
01 / 08

1,152 piles in Block B14. One of them is wrong.

Trackers go on next week. A sample walk would check forty of these piles and call the block ready.

02 / 08

Rowwalker finds it from a drone flight or phone photo.

Crew B photographs each pile from three angles as they walk off the row. No survey crew, no total station. The pile gets its ID from the IFC schedule and a record that follows it to COD.

03 / 08

Tilt: 3.2° against a 1.0° limit.

The reconstruction gives the pile axis. Against plumb it leans 3.2°, three times the OEM tolerance. A tracker set on this pile binds at the bearing and wears from day one.

04 / 08

Top of pile: 2.4 inches low.

Height is measured against the design elevation in the pile schedule, not the neighbour. Rotation is inside the limit, so the head is fine; the elevation is not.

05 / 08

Hardware: the stripe that is not there.

Every bracket bolt is checked for a torque witness mark. The plate shows corrosion at the cut edge, flagged for the coating crew before the row is released.

06 / 08

Condition: a 14 mm dent in the tube.

Handling damage is caught before the modules hide it. Depth is estimated from the reconstruction and flagged for the OEM to accept or reject.

07 / 08

Base: embedment and backfill pass.

Not everything fails. The record says so with the same evidence, so the owner’s engineer sees what passed and why.

08 / 08

Every pile gets a record. Two get re-driven.

T44-P03 and T47-P09 are re-driven before Thursday, re-measured, and closed. The rest of the row carries its proof into the certificate.

24 checks per pileTiltRotationHeightXYSpacingEmbedmentSlopeBearing alignmentTube straightnessSplice gapClamp gapBoltsTorque stripeCable routingCorrosionDentsAbrasionHandling damage+6
How it works

Capture. Measure. Prove.

Inspection drone over tracker rows
01

Capture

Your crew photographs each pile with a phone following our capture SOP, or our drone partners fly the block. Right after pile install, before trackers go on.

APIIntegrate Rowwalker into the capture devices you already run — drones, rovers, phone apps.
ServiceOr SunLean AI scopes the inspection as a service, capture included.
02

Measure

Rowwalker reconstructs every pile in 3D and compares it to the IFC pile schedule: tilt, rotation, height and XY, plus slope to ground, corrosion and dents — against the OEM's tolerances.

03

Prove

A design-vs-actual report and a live site map the whole team sees. Fix the two piles that are out before the row is built on them, and hand the owner a QC certificate when the block passes.

Flagship · Rowwalker

Pile and tracker verification, pile by pile.

Mechanical installation is where solar quality is won or lost, and where nobody has had objective data. Rowwalker gives every pile a record tied to its design position, and every deviation a number.

Piles
Tilt, rotation/torsion, height, XY, slope to ground, corrosion, dents.
Trackers and racking
Alignment against the design and the OEM manual.
Outputs
Design-vs-actual report, interactive site map, punch list, independent AI QC certificate.
Block B14 · 8 trackers · 224 piles · measured positions
T01T02T03T04T05T06T07T08B14-T01-P01B14-T01-P02B14-T01-P03B14-T01-P04B14-T01-P05B14-T01-P06B14-T01-P07B14-T01-P08B14-T01-P09B14-T01-P10B14-T01-P11B14-T01-P12B14-T01-P13B14-T01-P14B14-T01-P15B14-T01-P16B14-T01-P17B14-T01-P18B14-T01-P19B14-T01-P20B14-T01-P21B14-T01-P22B14-T01-P23B14-T01-P24B14-T01-P25B14-T01-P26B14-T01-P27B14-T01-P28B14-T02-P01B14-T02-P02B14-T02-P03B14-T02-P04B14-T02-P05B14-T02-P06B14-T02-P07B14-T02-P08B14-T02-P09B14-T02-P10B14-T02-P11B14-T02-P12B14-T02-P13B14-T02-P14B14-T02-P15B14-T02-P16B14-T02-P17B14-T02-P18B14-T02-P19B14-T02-P20B14-T02-P21B14-T02-P22B14-T02-P23B14-T02-P24B14-T02-P25B14-T02-P26B14-T02-P27B14-T02-P28B14-T03-P01B14-T03-P02B14-T03-P03B14-T03-P04B14-T03-P05B14-T03-P06B14-T03-P07B14-T03-P08B14-T03-P09B14-T03-P10B14-T03-P11B14-T03-P12B14-T03-P13B14-T03-P14B14-T03-P15B14-T03-P16B14-T03-P17B14-T03-P18B14-T03-P19B14-T03-P20B14-T03-P21B14-T03-P22B14-T03-P23B14-T03-P24B14-T03-P25B14-T03-P26B14-T03-P27B14-T03-P28B14-T04-P01B14-T04-P02B14-T04-P03B14-T04-P04B14-T04-P05B14-T04-P06B14-T04-P07B14-T04-P08B14-T04-P09B14-T04-P10B14-T04-P11B14-T04-P12B14-T04-P13B14-T04-P14B14-T04-P15B14-T04-P16B14-T04-P17B14-T04-P18B14-T04-P19B14-T04-P20B14-T04-P21B14-T04-P22B14-T04-P23B14-T04-P24B14-T04-P25B14-T04-P26B14-T04-P27B14-T04-P28B14-T05-P01B14-T05-P02B14-T05-P03B14-T05-P04B14-T05-P05B14-T05-P06B14-T05-P07B14-T05-P08B14-T05-P09B14-T05-P10B14-T05-P11B14-T05-P12B14-T05-P13B14-T05-P14B14-T05-P15B14-T05-P16B14-T05-P17B14-T05-P18B14-T05-P19B14-T05-P20B14-T05-P21B14-T05-P22B14-T05-P23B14-T05-P24B14-T05-P25B14-T05-P26B14-T05-P27B14-T05-P28B14-T06-P01B14-T06-P02B14-T06-P03B14-T06-P04B14-T06-P05B14-T06-P06B14-T06-P07B14-T06-P08B14-T06-P09B14-T06-P10B14-T06-P11B14-T06-P12B14-T06-P13B14-T06-P14B14-T06-P15B14-T06-P16B14-T06-P17B14-T06-P18B14-T06-P19B14-T06-P20B14-T06-P21B14-T06-P22B14-T06-P23B14-T06-P24B14-T06-P25B14-T06-P26B14-T06-P27B14-T06-P28B14-T07-P01B14-T07-P02B14-T07-P03B14-T07-P04B14-T07-P05B14-T07-P06B14-T07-P07B14-T07-P08B14-T07-P09B14-T07-P10B14-T07-P11B14-T07-P12B14-T07-P13B14-T07-P14B14-T07-P15B14-T07-P16B14-T07-P17B14-T07-P18B14-T07-P19B14-T07-P20B14-T07-P21B14-T07-P22B14-T07-P23B14-T07-P24B14-T07-P25B14-T07-P26B14-T07-P27B14-T07-P28B14-T08-P01B14-T08-P02B14-T08-P03B14-T08-P04B14-T08-P05B14-T08-P06B14-T08-P07B14-T08-P08B14-T08-P09B14-T08-P10B14-T08-P11B14-T08-P12B14-T08-P13B14-T08-P14B14-T08-P15B14-T08-P16B14-T08-P17B14-T08-P18B14-T08-P19B14-T08-P20B14-T08-P21B14-T08-P22B14-T08-P23B14-T08-P24B14-T08-P25B14-T08-P26B14-T08-P27B14-T08-P28N ↑
B14-T03-P11✕FAIL
Tilt 3.2° / ±2.0°
Rotation 4.1° / ±3.0°
ΔZ +2.8 cm / ±2.5 cm
50 m
PASS · 207FLAG · 15✕FAIL · 2Click any pile to open its record
Rowwalker defects view
Platform

One intelligence layer from IFC to COD.

Rowwalker is the flagship. Around it, SunLean is building the project-intelligence platform for solar construction.

Phase 01
Pre-construction screen

Pre-construction

Upload IFCs, geotech and pull-out tests; the AI reads them into actionable items before mobilization.

Phase 02
Earthworks QC: graded blocks compared to the planned surface, with cut and fill deviations flagged per block

Earthworks QC

Post-grading LiDAR vs the planned surface; pass or fix each block before release.

Phase 03 · Rowwalker
Construction QC live map

Construction QC

Pile and tracker verification with live maps and photos.

Phase 04
Certificates screenCommissioning punch list

Commissioning and handover

Punch list from the data, AI-backed certificates for owner, lender and OEM, handover to O&M.

Construction intelligence
Progress, cost and QC on one dashboard, read by the same agents.
Construction dashboard
Project and cost control
AI agents

The agents run the paperwork. A person signs it.

Upload the BOM, the IFC set and the OEM manual, connect the project inbox, and SunLean's agents work the day. One day on Block B14, as it happens.

SLBlock B14 · project assistant
Thu 6 Nov
ConnectedGmailBOM · SF7 rev 3IFC pile scheduleOEM manualCapturesProcore
Who it's for

The same report settles four conversations.

EPC

EPCs

Fewer QC walkers, less retraining, less rework, proof for the owner. Pay per MW, not per inspector.

Book a demo
Tracker OEM

Tracker OEMs

Verify the installation against your own manual before approving a warranty claim.

Book a demo
Owner · Lender · Insurer

Owners, lenders, insurers

An independent AI QC certificate on every block — engineering-grade evidence for financing and insurance.

Book a demo
O&M

O&M companies

A pile-by-pile baseline at handover. When a row underperforms in year one, the record shows whether it was built that way or moved since.

Book a demo
Why SunLean AI

Stop wasting time and money on manual quality checks.

Construction quality control shouldn't depend on endless inspections, repeated training cycles, and costly rework. SunLean AI automates verification so teams can focus on building — not chasing errors.

Book a demo
Eliminate hours of manual QA
Automated inspection analysis replaces slow manual reviews. Verify installation accuracy in minutes instead of hours.
Reduce training dependency
Quality checks are standardized through data, reducing constant retraining and the impact of labor turnover.
Prevent costly rework
Early detection of installation deviations lets teams correct issues immediately, before they compound.
Build with confidence
Every asset is documented with verifiable inspection data, visible to developers, EPCs and asset owners.
Aerial view of tracker rows on a solar site

Automate quality.
Protect every asset.

Company

Founded by engineers. Built for solar at scale.

We started SunLean AI after years of building, running and maintaining PV plants, and watching the same installation problems get found too late, by too few people, with too little evidence.

So we built the inspector we wished we had on site: one that measures every pile, keeps the photo, and gives the whole team the same numbers. From inspection to intelligence.

The SunLean AI team in hard hats and hi-vis in front of a tracker row
What we hold ourselves to

Three things we ask of ourselves, and that you can hold us to on your project.

Integrity
Trust is built on truth. Every decision should be grounded in data, and more importantly, results.
Accountability
Quality requires ownership. We stand behind outcomes and believe responsibility must be clear at every level.
Precision
The details matter. Small deviations today can become long-term consequences tomorrow.
Demo

See your own site measured.

Thirty minutes. We walk you through a real design-vs-actual report, then talk about which block of yours to measure first.

Not ready to talk? Get the sample report (anonymized PDF).
Next: choose a slot · 30 min